CMQ-OE Exam - Question 31


A benefit-cost analysis can best be used to:

Show Answer
Correct Answer:

Discussion

1 comment
Sign in to comment
ZeroLordOption: D
Apr 30, 2025

I think the best answer is D, since Benefit-cost analysis does not relate to team memebers performance answers B or C, or project cost with budget (CPI) answer A.