Question 40

A purchase order for subassemblies classified as critical must include a review by

I. Quality engineering.

II. The procurement department.

III. Design engineering.

    Correct Answer: D

    A purchase order for subassemblies classified as critical must be reviewed by the quality engineering department to ensure that the quality standards are met. The procurement department must be involved to handle the purchasing process and ensure the correct materials are ordered from approved suppliers. Design engineering must review to ensure the subassemblies meet design specifications and requirements. Therefore, all three departments (I, II, and III) should be involved in the review.

Discussion
Sachindra_89Option: D

Acceptable, design engineer is to be take decision accordingly.