PSP Exam QuestionsBrowse all questions from this exam

PSP Exam - Question 17


A security consultant is charged with designing security measures for a new facility. To ensure maximum effectiveness, the system should be designed:

Show Answer
Correct Answer: B,D

To ensure maximum effectiveness, the security system for a new facility should be designed at the inception of the project. This approach allows security considerations to be integrated into all phases of the project, ensuring that the facility's design accommodates security needs from the outset. This proactive strategy helps in identifying and mitigating potential vulnerabilities early, rather than retrofitting security measures later, which can be less effective and more costly.

Discussion

1 comment
Sign in to comment
buhljohnsonOption: B
Jan 16, 2024

This is incorrect. You never begin the design of a system during the RFP phase. You design it from the beginning - this goes against even CPTED.