PSP Exam QuestionsBrowse all questions from this exam

PSP Exam - Question 11


Which of the following items are part of the planning phase of project management?

Show Answer
Correct Answer: AD

During the planning phase of project management, a thorough threat assessment is conducted to understand potential risks, and design criteria are established to outline the necessary specifications and standards for the project. This ensures that the project objectives are met while mitigating potential risks and adhering to required standards.

Discussion

2 comments
Sign in to comment
d7703Option: D
Jul 31, 2023

a risk assessment report and design criteria are outputs of the planning phase

Casey04Option: D
Sep 4, 2023

D is correct - see IPPS pages 27 and 68