ASIS-CPP Exam QuestionsBrowse all questions from this exam

ASIS-CPP Exam - Question 68


Perhaps one of the most difficult tasks in planning for disaster and emergencies is the actual formulation of a basic disaster plan. Which of the following is an incorrect procedure in developing such a plan?

Show Answer
Correct Answer: C

In developing a basic disaster plan, it is critical to ensure that the plan is comprehensive and anticipates a wide range of potential emergencies, not just those that have occurred in the past. Limiting the types of emergencies to only those experienced by the company before is an incorrect procedure because it can leave the organization unprepared for new or unexpected crises. A robust disaster plan should consider diverse scenarios and include coordinated actions, necessary terminologies, and appendices such as maps and contact lists to effectively manage any potential disaster.

Discussion

3 comments
Sign in to comment
Brad626Option: C
Jan 11, 2020

Choices A and E are the same.

c_macleod78Option: C
Aug 15, 2020

C is correct per the POA

vera222Option: C
Sep 17, 2020

C is the correct answer. Emergency plan should not be limited with the past experience