In the scrum lifecycle of a project, when should the team agree on the requirements for the Definition of Done?
In the scrum lifecycle of a project, when should the team agree on the requirements for the Definition of Done?
In the Scrum lifecycle, the team should agree on the requirements for the Definition of Done (DoD) before getting started on the project. This is because having a clear understanding of what constitutes a completed task is crucial for ensuring that deliverables meet the necessary standards from the very beginning. Agreeing on the DoD helps in setting clear expectations, improving quality, and ensuring transparency within the team. It forms a foundational part of the initial planning phase and guides subsequent development activities.
The team should agree on the requirements for the Definition of Done before the start of the project, ideally during the initial sprint planning meeting. The Definition of Done can be revisited and revised during the project's lifecycle, but it's important to have a clear understanding of the requirements from the very beginning. Therefore I would argue that the right answer is A
Before getting started, teams need to make important decisions about how the extended team will work together during the project. These include: Scheduling the key ceremonies on a fixed cadence including: daily scrum, sprint planning, sprint review, backlog refinement, sprint review and the sprint retrospective. Design the development workflow and configure the project management tool (e.g. Jira). Define the deployment pipeline and configuration management process. Agree the Definition of Done (DoD) and Definition of Ready (DoR).
Scheduling the key ceremonies on a fixed cadence including: daily scrum, sprint planning, sprint review, backlog refinement, sprint review and the sprint retrospective Design the development workflow and configure the project management tool (e.g. Jira) Define the deployment pipeline and configuration management process Agree the Definition of Done (DoD) and Definition of Ready (DoR)
The correct Answer is D
Answer is A
Should be A
DoD falls under 'Agree on a Way of Working' which falls under the Initiate phase, which is also before the project kinda.
Correct is A. Before getting started, teams need to make important decisions about how the extended team will work together during the project. These include: Scheduling the key ceremonies on a fixed cadence including: daily scrum, sprint planning, sprint review, backlog refinement, sprint review and the sprint retrospective. Design the development workflow and configure the project management tool (e.g. Jira). Define the deployment pipeline and configuration management process. Agree the Definition of Done (DoD) and Definition of Ready (DoR). Resource: https://community.appian.com/success/w/guide/2973/the-appian-delivery-methodology
Correct option is A
DOD is checklist of things that should be available to determine if the story is complete. So this question is asking when do the team meets together and agree on what should be there in the DODs for all the stories. For example : we should have acceptance criteria for all the tests, we should have negative tests. This is not the actual DOD but agreement on what should be in DOD. So correct option is A. Before we start on the project. During Initiate Phase
A should be the ans