Which of the following types of lead times is related most closely to a supplier performance measure?

    Correct Answer: A

    Fulfillment lead time is the amount of time it takes from receiving an order to delivering the product to the customer. This metric is closely related to supplier performance because it directly measures how efficiently a supplier can fulfill orders, reflecting their reliability and speed in order processing and delivery.

Discussion
seeralanbOption: B

fulfilment is nor a leadtime type replenishment lead time–The total period of time that elapses from the moment it is determined that a product should be reordered until the product is back on the shelf available for use. Syn: reorder cycle.

SanjeyOption: A

Why not fulfillment lead time ?