A team has been given a project which requires them to design a new product with the following key performance indicators (KPIs) and prototype results:
What should be the next step of the project?
A team has been given a project which requires them to design a new product with the following key performance indicators (KPIs) and prototype results:
What should be the next step of the project?
The project should stay in the prototype phase and issue formal corrective action to address all key performance indicators. The table shows that while the prototype has met the acceptable limits for bill of material costs and the hours to produce one piece, it has not met the prototype yield KPI, which is below the acceptable level of 75% at only 60%. Moreover, since several indicators are close to their limits, it is critical to address all KPIs comprehensively to ensure the prototype performance aligns with all acceptable levels before moving to the production phase. This will help in identifying and resolving any potential issues that might arise during mass production.
why not B?
We have to remain in the prototype phase until all specifications are met. Right now we do not meet the "prototype yeld" but we must control that, as we improve this one, the others that are at the limit of the specification do not fall.
Should be B
Should be C
A is not correct