Exam CSCP All QuestionsBrowse all questions from this exam
Question 435

Which of the following events would initiate an update of a manufacturing site business continuity plan?

    Correct Answer: A

    A major renovation and asset consolidation program would initiate an update of a manufacturing site business continuity plan. Such changes can significantly alter the site's infrastructure, resources, and operational processes, necessitating a review and update of the plan to address new risks and ensure continuity. Events like power outages or supply interruptions, while critical, are typically covered within existing plans and don't usually warrant a complete update of the plan itself.

Discussion
igrdOption: A

A major renovation and asset consolidation program could significantly change the site's infrastructure, resources, and operational processes. As a result, it's important to update the business continuity plan to ensure it remains relevant and effective in managing potential risks and disruptions in the new operational context.

Rajiv8047Option: B

A power outage lasting more than 48 hours

[Removed]Option: B

B is correct