Exam CLTD All QuestionsBrowse all questions from this exam
Question 97

When looking at on organization's logistics system, which of the following expenses is the single largest variable cost?

    Correct Answer: B

    When looking at an organization's logistics system, transportation costs are typically the single largest variable cost. Transportation costs can fluctuate significantly based on fuel prices, shipping routes, and the volume of goods being moved. Inventory carrying costs, warehouse operations costs, and supply management costs are also important but generally more predictable and consistent compared to transportation costs.

Discussion
dailong142002Option: B

transportation costs is the single largest variable cost

Aziz8903Option: B

agree answer is B