Question 136

Which of the following outcomes is an expected benefit of effectively implementing supply chain event management software?

    Correct Answer: C

    Supply chain event management software is designed to monitor the progress of activities and alert stakeholders when there are deviations from the plan or expected outcomes. This enables organizations to respond quickly to issues as they arise, ensuring smoother operations and minimizing disruptions. Therefore, notifications of variances from plans being triggered is an expected benefit of effectively implementing such software.

Discussion
MahiSNOption: C

C is the correct answer because it is event management( Trigger of something)

shegzeeOption: A

I'd go with A

jiasidingcscp

Any thoughts?