A master production schedule (MPS) is designed to disaggregate:

Show Answer
Correct Answer: B

A master production schedule (MPS) is designed to disaggregate high-level product family plans into operational plans. The MPS takes the overall goals and forecasts for product families and breaks them down into detailed, time-phased production schedules. This allows for effective planning and allocation of resources to meet production requirements.

Discussion

2 comments
Sign in to comment
Rajiv8047Option: A
Dec 17, 2023

high-level planning into component requirements

limssng
Feb 5, 2024

no, about component is a MRP technique

WijithaOption: B
May 10, 2024

Product family plan to operational Plans