Exam API-580 All QuestionsBrowse all questions from this exam
Question 59

Potential hazards identified in a PHA will often affect the

    Correct Answer: B

    Potential hazards identified in a Process Hazard Analysis (PHA) often affect the consequence of failure side of the risk equation. In a PHA, possible scenarios and chains of events that can lead to hazardous outcomes are identified and explored, thus primarily focusing on determining the potential consequences if a failure occurs.

Discussion
89996feOption: B

Incorrect. Consequence. A PHA is a what-if analysis where possible chains of events are identified and explored.