Question 45

The programme that focused on maintaining the mechanical integrity of pressure equipment items and minimizing the risk of loss of containment due to deterioration

    Correct Answer: A

    Risk-Based Inspection (RBI) is a programme that focuses on maintaining the mechanical integrity of pressure equipment items and minimizing the risk of loss of containment due to deterioration. RBI evaluates the likelihood and consequences of failure to prioritize inspection resources and ensures that the most critical areas are inspected and maintained to prevent failures.