Question 1

RBI may include methodologies to assess the effectiveness of the management systems in maintaining

    Correct Answer: B

    The term 'total asset integrity' encompasses a broader scope, ensuring that all aspects of an organization's assets, including mechanical, structural, and process integrity, are maintained effectively. RBI (Risk-Based Inspection) methodologies are typically aligned with ensuring the overall integrity of assets rather than focusing solely on mechanical aspects or limiting it to a specific part like the plant.

Discussion
AncestOption: A

looking 5.7.3