The primary work products of the RBI assessment and management approach and implementation of RBI provides

    Correct Answer: A

    The primary work products of the Risk-Based Inspection (RBI) assessment and management approach aim to reduce overall risk while accepting the current level of risk as being manageable. The goal of RBI is to prioritize inspections and maintenance based on the risk posed by different components, ultimately seeking to reduce the likelihood and consequence of failures. Therefore, the most accurate option is overall reduction of risk and acceptance of current risk.