RBI is based on

    Correct Answer: A

    RBI (Risk-Based Inspection) is based on sound, proven risk assessment and management principles. It is a systematic process that evaluates the probability of failure and the consequences of failure, aiming to prioritize inspection resources on the high-risk areas. This helps in optimizing inspection and maintenance schedules, ensuring safety, reliability, and integrity of the assets.