Question 6 of 50
What emerges from self-organizing teams?
A.
The best process flows, user stories and requirements
B.
The best architecture, requirements and designs
C.
The best designs, user stories and Sprint backlog
D.
The best architecture, user stories and requirements
Answer
Discussion
Correct Answer: B
Question 7 of 50
Daily Scrum is used to:
A.
inspect and adapt work.
B.
assign tasks.
C.
demo the changes to Stakeholders.
D.
estimate the pending work.
Answer
Discussion
Correct Answer: A
Question 8 of 50
In which event are impediments to the Sprint Goal shared?
A.
Daily Scrum
B.
Sprint Planning
C.
Sprint Retrospective
D.
Sprint Review
Answer
Discussion
Correct Answer: A
Question 9 of 50
Developers asking for help or admitting not knowing something best demonstrates which Scrum Value?
A.
Respect
B.
Courage
C.
Commitment
D.
Focus
Answer
Discussion
Correct Answer: B
Question 10 of 50
Which of the following is a required attribute of a Product Backlog item (PBI)?
A.
Assigned to
B.
Size
C.
Due Date
D.
State
Answer
Discussion
Correct Answer: B