Question 6 of 80You have concluded a cleaning contract with a supplier for your operating facility. You agreed on a monthly amount for which you want to automatically create a credit note every month. What do you use in this scenario?
Correct Answer: B
Question 7 of 80Which of the following steps can be part of a subcontracting process? (Choose three.)
Correct Answer: B, D, E
Question 8 of 80What must you do when using supplier consignment? (Choose two.)
Correct Answer: B, C
Question 9 of 80You create a blanket purchase order for several minor repairs that may occur during the year. Which of the following data must you enter? (Choose two.)
Correct Answer: A, C
Question 10 of 80Which of the following actions are supported when you post a goods receipt to stock with reference to a purchase order? (Choose three.)