Question 6 of 80Which of the following parameters are available when you define a new maintenance plan category? (Choose three.)
Correct Answer: A, B, C
Question 7 of 80You want to create a single-cycle plan with a cycle of 12 months. You use the scheduling indicator Time - key date. The orders should be called 3 months before the planned date. How can you set up the maintenance plan? (Choose two.)
Correct Answer: C
Question 8 of 80You want to set up a general maintenance task list for inspection rounds using the overall time confirmation as a simplified way to record measurement documents. What do you need to do? (Choose two.)
Correct Answer: A, B
Question 9 of 80You create two maintenance packages and only one package should be executed at a time. Which parameter determines this?
Correct Answer: B
Question 10 of 80You want to set up a scenario for regular maintenance. The first event should take place after 1 year; after that, it is a regular cycle of 6 months. Which parameter do you have to use to map this in the system?