Question 6 of 76The technical completion of the current maintenance order was posted with a delay of 5 days. What happens to the next planned date if you set the shift factor for early completion to 100%?
Correct Answer: B
Question 7 of 76You want to assign a maintenance planning plant directly to an organizational unit. Which of the following units can you use?
Correct Answer: B
Question 8 of 76Which operations can the responsible person perform after a maintenance order is technically completed? (Choose three.)
Correct Answer: B, C, E
Question 9 of 76You require stock material to carry out maintenance tasks. Which of the following statements regarding material planning in the maintenance order are correct? (Choose three.)
Correct Answer: A, C, E
Question 10 of 76Which statements about the structure indicator are correct? (Choose two.)