Question 6 of 120
A large railway project is in the planning stage, and different options have been evaluated. A technical paper is published describing technology that may increase the efficiency of the transport route. However, the technology comes at a significant cost increase. The company tasked with the railway design needs to determine if they should consider making changes based upon the study.
What should the construction professional do to determine this request?
Correct Answer: A

Question 7 of 120
A construction professional is working on a large complex project to build a first of its kind technology. The project is progressing toward detailed design and is required to go through a phase gate that must include a detailed risk register. The construction professional has identified a number of risks that may require contingency.
What should the construction professional do?
Correct Answer: B

Question 8 of 120
A construction project to build a mixed commercial-residential development is in the planning phase. The project has many stakeholders and multiple communications channels. The construction professional analyzes stakeholders and has identified one stakeholder who has high interest in the project but low influence, so the construction professional decides to exclude this stakeholder from any project communications to reduce the number of communications channels.
What will be the predicted outcome of the construction professional's decision?
Correct Answer: B

Question 9 of 120
A project management office (PMO) is auditing a construction project and its delivery when they discover that the project does not have a risk register. The project manager believes that the daily standups are a better way to manage risks. The PMO approaches a construction professional to help with this situation.
How should the construction professional respond to the project manager to help them understand the need for the risk register?
Correct Answer: B

Question 10 of 120
A construction project is in the planning phase of building a desalination plant. The construction professional's team has identified and logged a risk in the risk register, noting multiple root causes and has assigned responses to address each cause.
How should the construction professional manage this risk moving forward?
Correct Answer: A