Question 6 of 75
A customer wants to validate the Microsoft SQL workload performance for a CRM application before migration to the new Nutanix cluster.
Which activity must the consultant add as part of the test plan to fulfill this requirement?
Suggested Answer: B

Community votes

No votes yet

Question 7 of 75
After an onsite cluster deployment, a consultant prepares the deliverables for a project closeout.
Which two data in the As-Built Guide require adjustment or might be missing completely? (Choose two.)
Suggested Answer: B, C

Community votes

No votes yet

Question 8 of 75
In preparing to install a new cluster for a company, a consultant needs to complete an installation worksheet.
Which values must be documented prior to initial base system setup?
Suggested Answer: A

Community votes

No votes yet

Question 9 of 75
At which prompt should a consultant execute the command manage_ovs - bridge_name br0 show_uplinks in a Nutanix cluster?
Suggested Answer: D

Community votes

No votes yet

Question 10 of 75
The installation process stops before imaging any of the nodes and an error message is displayed notifying the IPMI IP address is unreachable.
What should consultant do to fix the issue?
Suggested Answer: A

Community votes

No votes yet