You need to track progress for the current sprint.
Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.)
You and the team need to select user stories for the next sprint.
What should you do?
The team has identified items from the product backlog for the next sprint.
You need to ensure that the team has adequate capacity to complete the next sprint.
Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.)
It is critical that all issues identified as potential bugs get addressed in a timely manner.
You need to ensure that incident response times are managed across support and development teams.
What should you do?
The system is too large to perform a manual smoke test.
You need to ensure that the latest release to production has not broken anything.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)