Question 6 of 40
Which tasks are typically performed by a tester on an Agile project? i) Implementing test strategy. ii) Documenting business requirements. iii) Measuring and reporting test coverage. iv) Coaching development team in relevant aspects of testing. v) Executing test-driven development tests.
Correct Answer: A

Question 7 of 40
Which of the following statements would you expect to be the MOST direct advantage of the whole-team approach?
Correct Answer: D

Question 8 of 40
You are working on an Agile project and have been asked to implement exploratory testing for the current sprint. Which one of the following is a correct approach to adopt?
Correct Answer: B

Question 9 of 40
You have been asked to execute an exploratory testing session on Park & Ride system. The test charter has been titled as "Buy a bus ticket". As a result, a number of defects were reported, the titles of which are listed below.
Which defect is out of scope for the given test charter?
Correct Answer: D

Question 10 of 40
What is the definition of agile software development?
Correct Answer: A