Question 6 of 64
You are following a risk-based testing strategy. The test execution time is very limited. Assume that all the product risk items require more or less the same level of test effort.
Exam CTAL-TM_Syll2012: Question 6 - Image 1
Which of the following answers describes the best execution schedule in this scenario?
    Correct Answer: D

Question 7 of 64
Assume that the following test cases have been executed at the end of the first week of test execution: TC-001, TC-002 and TC-007. All these tests are ‘passes’.
What is the MINIMUM number of the remaining test cases that must be successfully executed to fulfill the EX1 exit criteria?
Exam CTAL-TM_Syll2012: Question 7 - Image 1
    Correct Answer: A

Question 8 of 64
Assume that no additional product risks have been identified during the first week of test execution.
Exam CTAL-TM_Syll2012: Question 8 - Image 1
Exam CTAL-TM_Syll2012: Question 8 - Image 2
Which of the following answers would you expect to best describe the residual risks associated with the identified product risks, at the end of the first week of test execution?
    Correct Answer: D

Question 9 of 64
Testing Process -
The following are the exit criteria described in the test plan of a software product:
EX1. The test suite for the product must ensure that at least each quality risk item is covered by at least one test case (a quality risk item can be covered by more test cases).
EX2. All test cases in the test suite must be run during the execution phase.
EX3. Defects are classified into two categories: “C” (critical defect) and “NC” (non-critical defect). No known C defects shall exist in the product at the end of the test execution phase.
Which of the following information is useless when the specified exit criteria is evaluated?
    Correct Answer: C

Question 10 of 64
Testing Process -
Which of the following is an example of the test closure activity indicated as "lessons learned"?
    Correct Answer: C