Which part of the sales cycle is not supported by the Smart Grid PDI Help Desk?
A.
operation
B.
implementation
C.
design
D.
planning
Answer
Discussion
Correct Answer: A
Question 7 of 23
Why is IEC 61850 important within the energy / utility industry?
A.
a new routing protocol for electricity
B.
the latest Cisco product for connected grid security
C.
a law recently passed in the United States
D.
define industry standard for design of electrical substations
Answer
Discussion
Correct Answer: D
Question 8 of 23
Which three of these methods can be used to open a Cisco TAC case? (Choose three.)
A.
using the U.S. Postal Service
B.
email
C.
using Cisco.com
D.
by fax
E.
phone
Answer
Discussion
Correct Answer: B, C, E
Question 9 of 23
Following is NOT atypical business driver for upgrading Substation communications networks?
A.
overall grid reliability
B.
industry regulation and standards compliance
C.
generating new revenues for the utility reducing operational expenses
Answer
Discussion
Correct Answer: C
Question 10 of 23
Which two can use the Smart Grid PDI Help Desk? (Choose two.)
A.
internal Cisco sales team members
B.
anyone with a CCO ID
C.
trained employees from our Connected Grid Partner
D.
everyone
E.
all Gold partners
Answer
Discussion
Correct Answer: C, E