Question 6 of 60Your company is rolling out Skills and Certifications to encourage employees to track their skills and also decide which skills they would like to acquire. After rolling this feature out, end-users have noted they can't add their assignments to build their "Experience". What could be causing this problem?
Correct Answer: C
Question 7 of 60Currently Project Managers and Resource Managers are using Gantt. You do not want your Project Managers creating assignment, resource requests or milestones from the Gantt. Which of the following custom settings should you configure to hide these buttons?
Correct Answer: B
Question 8 of 60In your organization, you always send 2 separate invoices to your customers – one for Timecards & Expenses and the other for Misc Adjustment type billable records. How could this be done automatically using FinancialForce functionality?
Correct Answer: A
Question 9 of 60In your Company, a Resource Manager wants to provide the option for Resources to nominate themselves for upcoming work they are interested in. How can you set this up?
Correct Answer: A
Question 10 of 60A Services manager has asked you to set up a unique "FF Navigation" lightning component on the "Services Delivery Workspace" that will provide separate options to users based on which team (business unit) they belong to. Which two of the following actions would successfully accomplish the required setup? (Choose two.)