Question 1 of 68

When creating a new Inspection form, a client requires a Work Order to be created if certain responses are recorded. Which two actions are required for this to be achieved? (Choose two.)

    Correct Answer: A, C

    To create a Work Order based on specific responses in an Inspection form, the first action to accomplish this is to choose 'Work Order' on the question action. This sets a trigger directly associated with the response to generate a Work Order. The second necessary action is to add an Action Script in the Form Settings, which can be customized to define and implement the logic needed to produce a Work Order from the specific responses captured in the form.

Question 2 of 68

In which three applications can Asset Depreciation be configured? (Choose three.)

    Correct Answer: C, D, E

    Asset Depreciation can be configured in Asset Templates, Locations, and Assets. Asset Templates allow you to apply depreciation settings to multiple assets using a template. Locations enable you to manage depreciation at the place where assets are used. Assets application allows direct configuration of depreciation on individual assets.

Question 3 of 68

How is the Lock Out / Tag Outs application structured?

    Correct Answer: B

    The correct structure for Lock Out / Tag Out applications typically involves specifying a Lock Out on the Location or Asset and defining the Tag Out Operations. This ensures that the hazardous energy is properly controlled and the tag is used to communicate the lockout status to prevent accidental energization.

Question 4 of 68

What are three available associations in the Hazards application? (Choose three.)

    Correct Answer: C, D, E

    The three available associations in the Hazards application are Hazardous Materials, Tag Outs, and Precautions. These elements are crucial for managing and mitigating risks associated with hazardous conditions and ensuring safety protocols are followed.

Question 5 of 68

In the Assets application a used engine needs to be replaced with a rebuilt engine, how might the rebuilt engine inherit the depreciation schedule from the used engine?

    Correct Answer: C

    To ensure the rebuilt engine inherits the depreciation schedule from the used engine, the correct action to use is 'Swap Depreciation Schedules'. This action allows for the swapping of depreciation schedules between assets, thus seamlessly transferring the schedule from the old engine to the rebuilt one.