Question 6 of 55


An extract of a permission scheme is shown below.

Jennifer Evans needs to be able to:

✑ Manage project role membership

✑ Log time to issues

What is the minimum number of project roles she needs?

    Correct Answer: D

    Jennifer Evans needs the 'Administer Projects' permission to manage project role membership and the 'Work on Issues' permission to log time to issues. According to the permission scheme, the 'Administer Projects' permission is granted to the 'Administrators' role, and the 'Work on Issues' permission is granted to the 'Users' role. Therefore, she needs a minimum of two project roles: 'Administrators' and 'Users'.

Question 7 of 55


Teresa is able to see the Start Progress transition but not the Approve transition on an issue. Her co-worker is able to see both.

Identify two possible causes why Teresa can NOT see the Approve transition. (Choose two.)

    Correct Answer: CD

    Teresa's inability to see the Approve transition could be due to two main reasons: she might not be in the correct group or project role, or she might not meet the condition set on the Approve transition. These factors would affect her visibility of specific transitions while allowing her to still see others like Start Progress.

Question 8 of 55


You are the project administrator handling configuration changes requested by the users.

Whenever possible, you want to handle the changes yourself without involving the Jira administrator.

Which two changes might be possible for you to handle yourself? (Choose two.)

    Correct Answer: CD

    As a project administrator in Jira, you can manage users and their permissions within a project. Therefore, you can handle assigning Sam Smith the same permissions as Dwayne Johnson. Additionally, you can manage who has the ability to bulk-edit issues by configuring the project's permissions scheme to restrict this action to QA managers. On the other hand, changing priority values, setting up notifications, and modifying issue security levels typically require Jira administrator rights.

Question 9 of 55


Tom needs to work on scheduling and reordering future Sprints in a project.

What are the minimum two permissions that Tom needs? (Choose two.)

    Correct Answer: EF

    To work on scheduling and reordering future Sprints, Tom needs 'Schedule Issues' to manage the timing and ordering of tasks within the sprints, and 'Manage Sprints' to create, edit, and reorder the sprints themselves. These permissions are essential for handling sprints effectively.

Question 10 of 55


Security levels have already been configured in the Legal project's issue security scheme.

Now Dave needs to be able to set a particular security level on an issue in the Legal project. Identify three prerequisites for him to be able to do this. (Choose three.)

    Correct Answer: ABC

    In order for Dave to set a particular security level on an issue in the Legal project, he must first be assigned to that particular security level to ensure he has the appropriate clearance. He also needs the Set Issue Security permission in the Legal project to execute the action. Lastly, Dave must have access to the Legal project itself to interact with its issues. The prerequisites of being a project administrator or having a Jira Software license are not necessarily required for setting an issue's security level. Additionally, the question states that security levels have already been configured, implying that issue-level security is already globally enabled.