Exam OG0-093 All QuestionsBrowse all questions from this exam
Question 341

In which ADM phase is the Implementation and Migration Plan coordinated with other activities in the enterprise?

    Correct Answer: E

    In the TOGAF ADM, Phase F: Migration Planning is where the Implementation and Migration Plan is coordinated with other activities in the enterprise. This phase is focused on finalizing the Architecture Roadmap and the supporting Implementation and Migration Plan, ensuring that these plans are aligned with the enterprise's approach to managing and implementing change.

Discussion
noureldinOption: E

13.1 Objectives Ensure that the Implementation and Migration Plan is co-ordinated with the enterprise's approach to managing and implementing change in the enterprise's overall change portfolio https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap13.html

PrashanttheCloudMasterOption: E

Correct Answer 3.1 Objectives The objectives of Phase F are to: Finalize the Architecture Roadmap and the supporting Implementation and Migration Plan Ensure that the Implementation and Migration Plan is co-ordinated with the enterprise's approach to managing and implementing change in the enterprise's overall change portfolio Ensure that the business value and cost of work packages and Transition Architectures is understood by key stakeholders