In which phase of the ADM cycle do building blocks become implementation-specific?

    Correct Answer: E

    In Phase E of the ADM cycle, building blocks become more implementation-specific. During this phase, building blocks are specified as Solution Building Blocks (SBBs), making their interfaces and architecture more detailed and product-specific.

Discussion
noureldinOption: E

Building Blocks and the ADM Building Block Specification Process in the ADM Finally, in Phase E the building blocks become more implementation-specific as SBBs, and their interfaces become the detailed architecture specification. The output of Phase E is the building block architecture, both in ABB (i.e., functionally defined) and SBB (i.e., product-specific) forms. https://pubs.opengroup.org/architecture/togaf8-doc/arch/chap32.html#:~:text=Finally%2C%20in%20Phase%20E%20the,%2C%20product%2Dspecific)%20forms.