Complete the sentence. The TOGAF risk categorization after the implementation of mitigating actions is known as the level of risk.

    Correct Answer: D

    The TOGAF framework defines the 'residual' level of risk as the risk remaining after mitigating actions have been implemented. This categorization helps in understanding the effectiveness of the mitigation and what risks still need to be managed.

Discussion
noureldinOption: D

27.1 Introduction There are two levels of risk that should be considered, namely: Initial Level of Risk: risk categorization prior to determining and implementing mitigating actions Residual Level of Risk: risk categorization after implementation of mitigating actions (if any) https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap27.html