Question 80

The director of engineering in your organization always stresses the importance of meeting deadlines in order for the engineering department to be seen as a reliable source for the product management department. The director has calculated that the team's velocity needs to increase an additional 15% to meet the commitment he made to management for the release date of the product.

He asks Steven, the team's Scrum Master, to increase his team's velocity. Which would be the best two responses for Steven to take? (Choose two.)

    Correct Answer: B, C

    The best two responses for Steven involve taking actionable steps to improve productivity and aligning with Scrum principles. First, by informing the director of organizational impediments and suggesting collaboration to remove these impediments, Steven takes a proactive approach to address factors that hinder the team's productivity. Second, by educating the director about the team's self-organization and inviting him to the Sprint Retrospective, Steven aligns with Scrum principles, which emphasize team autonomy and continuous improvement. This fosters a culture of collaboration and empowerment without imposing external pressure, which is crucial for sustainable velocity improvement.

Discussion
madrid99Options: BC

D is incorrect because neither the Scrum Master (nor the PO) can force the dev team to speed up. Speed is calculated by the dev team, and the sprint goal represents the commitment. Thus there's no commitment for hard deadlines or having items done during the sprint. Speed is not the first measure to success, but "done" product increment.

amogOptions: AB

A and B are correct, but don't know why D is incorrect

Shariq

Stakeholders should not be attending Sprint Retro because these meetings are intended to be a safe space for the Development Team to discuss internal processes and improvements without external pressure.

NhungNhungOptions: AD

A and D

LuckyAroOptions: BC

B. By addressing organizational impediments, Steven is taking a proactive approach to identify and eliminate obstacles that hinder the team's productivity. Collaborating with the director to remove these impediments can lead to tangible improvements in the team's velocity. C. Highlighting the concept of self-organization and inviting the director to the Sprint Retrospective aligns with the Scrum framework's principles. This allows the team to reflect on their performance, identify areas for improvement, and collaboratively find solutions. Involving the director in this process fosters a culture of continuous improvement and teamwork.

Shariq

Stakeholders should not be attending Sprint Retro

bzubOptions: AB

D can't be true as velocity is a measure for predictability not a measure for success. value is the measure for success.

572f16dOptions: BD

B and D

ferutOptions: BD

D is correct. B is true for specific situation: there are impediments, and those are which the director can be a help of. Sometimes the team needs just to speed up at the beginning and this is not necessarily an impediment.

nhungnt184Options: AB

A and B.