Exam PMP All QuestionsBrowse all questions from this exam
Question 1057

A project team is executing a project to replace an existing system with a new one. A new project manager has been hired and observes that the team consist of professionals who have worked with the older system, and others who have little previous experience.

What should the project manager do to ensure project success?

    Correct Answer: A

    To ensure project success, it is important for the project manager to first evaluate the current effectiveness of the team and define development needs. This involves assessing the skills, experience, and strengths of each team member. This evaluation allows the project manager to identify any gaps and decide on necessary training or adjustments needed for the team to work effectively together, thereby increasing the chances of project success.

Discussion
ju3504Option: C

I thick that correct answer is C.

AbdelmonmOption: A

In this scenario, the new project manager should start by evaluating the current effectiveness of the team. This involves assessing the skills, experience, and strengths of individual team members. Understanding the strengths and development needs of the team will allow the project manager to make informed decisions about how to leverage the existing skills and address any gaps. This evaluation will contribute to building a cohesive and effective team for the successful execution of the project.