During the execution of a multi-million dollar project, the project manager learns of the theft of important installation materials at one of the most time-critical sites.
The project manager contacts the risk manager to discuss further steps, based on the risk register and the defined risk strategy for the risk of theft. However, the risk manager clarifies that the risk of theft was not identified in the risk management process.
What should the project manager do next?