As a project is reaching completion, the project sponsor tells the project manager to immediately close the project and to move on to another project. Which critical task should the project manager complete before closing the project?
As a project is reaching completion, the project sponsor tells the project manager to immediately close the project and to move on to another project. Which critical task should the project manager complete before closing the project?
Before closing the project, it is crucial to update and close both the risk register and issue log with the latest updates and save them in the organization's project management information system (PMIS). This ensures that all potential risks and issues have been addressed or documented, providing a comprehensive record for future reference, audits, and lessons learned. Properly closing these logs aligns with standard project management practices and ensures compliance with organizational requirements.
Ensuring that the risk register and issue log are updated and closed with the latest information is crucial for maintaining accurate project records. This documentation is vital for future reference, audits, and lessons learned. Properly closing the risk register and issue log ensures that all potential risks and issues have been addressed or documented. This helps in preventing unresolved problems from affecting future projects. Updating and saving these documents in the organization's PMIS aligns with standard project management practices and ensures compliance with organizational requirements.
in the closing phase, First step update risk register and issue log