Question 155

A project is at the final development stage. The test lead informs the risk manager that a key feature may not be testable due to changes in the environment. What should the risk manager do?

    Correct Answer: C

    The risk manager should escalate the issue to the project board. At the final development stage, an untestable key feature poses a significant risk to the project's success. Escalating the issue ensures that it gets the appropriate level of attention and decision-making authority to resolve it promptly. The project board can mobilize the necessary resources or make strategic decisions to address the risk effectively.

Discussion
MikeMarloOption: A

Understanding and addressing the current issue. If team cannot do it with this new change in the environment, we should to C.