A project is at the final development stage. The test lead informs the risk manager that a key feature may not be testable due to changes in the environment. What should the risk manager do?
A project is at the final development stage. The test lead informs the risk manager that a key feature may not be testable due to changes in the environment. What should the risk manager do?
The risk manager should escalate the issue to the project board. At the final development stage, an untestable key feature poses a significant risk to the project's success. Escalating the issue ensures that it gets the appropriate level of attention and decision-making authority to resolve it promptly. The project board can mobilize the necessary resources or make strategic decisions to address the risk effectively.
Understanding and addressing the current issue. If team cannot do it with this new change in the environment, we should to C.