Question 291

A project manager has the task of determining the deliverables for a six-month project using a predictive approach. How should the project manager determine which processes to include in the project management plan?

    Correct Answer: D

    For a project using a predictive approach, it is essential to follow established organizational methodologies to ensure all required deliverables are produced. The predictive approach relies on detailed upfront planning and a clear sequence of processes. By adhering to organizational guidelines and ensuring that all mandatory deliverables are created, the project manager can effectively manage the project and meet its objectives. This ensures consistency, compliance, and alignment with organizational standards and best practices.

Discussion
ebbff63Option: B

Ans:B Discuss the processes and deliverables needed to meet the project objectives with the team.