Exam PgMP All QuestionsBrowse all questions from this exam
Question 139

A program is completed and the expected benefits are realized.

Before executing the transition and closing of the program, what should the program manager do?

    Correct Answer: C

    Before executing the transition and closing of the program, the program manager should obtain approval from the program governance board to initiate program closure activities. This is crucial to ensure that all stakeholders are in agreement that the program has met its objectives and that it is appropriate to start the closure process. Approval from governance confirms that the program is ready for closure and proper procedures can be followed afterward.

Discussion
tsangcklOption: C

C , get the approval first

NonstopLearningOption: A

as per eco, below are the activites: 1. create program peformance analysis report 2. seek approval 3. transition/sustaining activities, administrative closure 4. post review meeting 5. archieve docs hemce i think answer should be A as it's the 1st step.

hanyulinOption: C

C is the correct answer.

[Removed]Option: C

C. Obtain approval from the program governance board to initiate program closure activities

[Removed]

If the LAST step is asked, than Lessons learned.

hanyulinOption: A

C is the correct answer.

Amr1980Option: C

I think Governance board will be needed in phase exit where to finally closing the program ; so you need to do the Archiving ; Lesson learned and final Program report ; after call for meeting with program governance to review and accept to proceed with program closing