Question 1207

A new agile project is starting. The project manager is asked to confirm the scope to address the concerns of one of the stakeholders.

What should the project manager use to explain the project scope?

    Correct Answer: B

    To explain the project scope in an agile project, the project manager should use the product backlog. The product backlog is a comprehensive and prioritized list of all the features, enhancements, and fixes required for the product, representing the entire scope of the project. It serves as a single source of truth for the work being undertaken and provides a clear overview of what needs to be addressed to deliver the product, meeting the stakeholder's concerns.

Discussion
kevzzzOption: B

The product backlog encompasses the entire project scope. It serves as a long-term, prioritized list of all features, enhancements, and fixes necessary for the product.