A program is developing a next-generation product line, and one component has been delivered. However, due to a change request, expectations for another component are unmet.
What activity should the program manager perform next?
A program is developing a next-generation product line, and one component has been delivered. However, due to a change request, expectations for another component are unmet.
What activity should the program manager perform next?
When expectations for a component are unmet due to a change request, the program manager should perform program performance monitoring and controlling activities. This involves tracking, reviewing, and regulating the program's progress and performance to ensure alignment with the program plan. It helps identify discrepancies, assess impacts of changes, and take corrective actions to keep the program on track towards achieving its objectives.
In the scenario where a program is developing a next-generation product line and faces an issue with unmet expectations for a component due to a change request, the next activity that the program manager should perform is: C. Program performance monitoring and controlling. This activity involves continuously tracking, reviewing, and regulating the progress and performance of the program. It helps to identify any areas that are not aligning with the program plan, such as the unmet expectations due to the change request, and enables the program manager to take corrective actions. This process includes managing changes, assessing impacts, and ensuring that the program's objectives are still achievable. It is essential for addressing issues promptly and keeping the program on track towards its goals.
C. Program performance monitoring and controlling. This activity involves assessing the current performance of the program components, understanding the impact of the change request, and making decisions to bring the unmet component back in line with program expectations. It is an integral part of ensuring that the program adapts to changes while still meeting its overall objectives and delivering the expected benefits. Monitoring and controlling program performance will likely involve analyzing the situation, identifying corrective actions, and implementing those actions to address the discrepancies caused by the change request. This may also include updating the program management plan, communicating with stakeholders, and managing the expectations around the delivery of the program's components.
Agree, with those who responded with same answer. Because unmet expectations of a component are an issue with the program and will be addressed through monitoring and control phase of the program.
A is the right answer.
B is the right answer, during the execution PM is responsible to deploy resources between components