Exam PMI-SP All QuestionsBrowse all questions from this exam
Question 7

You are the project manager of the GHT Project. Ben, one of your project team members, does not understand the idea of a milestone. Which of the following best describes what a milestone is?

    Correct Answer: A

    A milestone is a significant point or event in the project. It marks important stages in the project lifecycle, signifying the completion of major phases or key deliverables. Milestones serve as checkpoints to assess the project's progress, but they do not necessarily have to be linked to specific dates. They help in evaluating performance and guiding the direction of the project.

Discussion
omankomanOption: A

A is right answer.