Exam CAPM All QuestionsBrowse all questions from this exam
Question 305

A project team has completed the first iteration and the testing manager approved the test report, indicating that the acceptance criteria have been met. The manager of the business unit that will use the new product is asking for additional functionality before approving the rollout for their team.

What should the project manager do next?

    Correct Answer: B

    Once the testing manager has approved the test report and the acceptance criteria have been met, it means the product is ready for rollout as per the project's predefined scope. If the business unit manager requests additional functionality, the project manager should address this new requirement. The appropriate action would be to reschedule the rollout to include the new requirements, ensuring the product meets the updated needs of the business unit before deployment. This approach minimizes changes after deployment and aligns the product with the expected deliverables of the business unit.

Discussion
ebbff63Option: C

Ans: C The project sponsor has the authority to make decisions regarding scope changes and can provide guidance on how to proceed with the additional functionality request.