Question 72

Which of the following success factors will enhance the Perform Qualitative Risk Analysis process as the risk occurrence gets closer?

    Correct Answer: B

    As the risk occurrence gets closer, iterative analysis becomes a critical success factor in the Perform Qualitative Risk Analysis process. This allows for continuous re-evaluation and refinement of risk information, ensuring that the analysis remains current and relevant as project conditions change.

Discussion
ahmedSayisOption: D

D. Agreed-upon approach

hossam83Option: D

D is the right answer

Azharmak

Key Success factors at 4.4.2 in Standard for Risk are: 1. Use Agreed Approach 2. Use Agreed definitions of Risk terms 3. Collect credible information about risk 4. Perform iterative qualitative risk analysis So more than one answers are correct.........

aws_guru1Option: D

The correct answer is D. I don't know who is providing the answers for Exam Topic.

MikeMarloOption: C

Closer means High Quality Information >> Clarification over time. Approach and definitions should be defined and not be changing around. Iterative analysis could be to monitor closely the risk about to happen. Normally, Success factors go as below: 1. Approach 2. Definitions 3. High Quality 4. Iterations

sheraship22

Azharmak is correct. Per practice standard for RM, section 6.2, all of the answers are key success factors in perform qualitative analysis. https://www.pmi.org/-/media/pmi/documents/public/pdf/certifications/practice-standard-project-risk-management.pdf?v=1e0b5985-74af-4c57-963c-b91a9af6fecb

AzharmakOption: D

Surely D Please

muhammadidrees87_Option: B

The success of qualitative risk analysis is enhanced if the process is used periodically throughout the project. (PRACTICE STANDARD),, Answer B iterative

LunkOption: D

Standard for risk management, 4.4.2 says agreed upon approach first.