Question 96

At what point in the project is the risk of failing to achieve the project objectives the greatest?

    Correct Answer: C

    The risk of failing to achieve the project objectives is greatest at the project start. This is because at the beginning of the project, there is a higher level of uncertainty and less information available. As the project progresses, risks are identified, analyzed, and mitigation plans are put in place, reducing the overall risk.

Discussion
LuanND

I really can't map the answer. Please help me for detail plz.