A project manager has determined that an activity is too complex to complete internally so they hire a licensed contractor to complete the work. What is the project manager performing in this situation?
A project manager has determined that an activity is too complex to complete internally so they hire a licensed contractor to complete the work. What is the project manager performing in this situation?
When a project manager hires a licensed contractor to complete work that is too complex to handle internally, they are engaging in risk transfer. This means they are shifting the responsibility and liability for that specific task from the internal team to an external party, in this case, the contractor.
too risky to do it internally and hiring a contractor, then it is a transfer.
B is correct
The question defines transfer - B
B = Transfer is the correct answer.