Exam PMI-RMP All QuestionsBrowse all questions from this exam
Question 157

During project execution, a project manager invites the stakeholders to a risk review meeting. During this meeting, a vendor highlights that the mitigation plan for a schedule risk has generated an additional risk.

What should the risk manager do first?

    Correct Answer: A

    When a new risk is identified, the first step is to update the risk register to document the risk. This ensures that it is formally recognized and can be tracked and managed. Only after the risk is documented should responses be planned. This documentation process is crucial to maintaining a comprehensive and up-to-date risk management plan.

Discussion
MikeMarloOption: A

A new risk is generated, so we included in the Risk Register *first*

MikeMarlo

include it*