Which of the following scheduling techniques identifies the successor activities and the predecessor activities to assist the project manager in sequencing the project work?
Which of the following scheduling techniques identifies the successor activities and the predecessor activities to assist the project manager in sequencing the project work?
The Precedence Diagramming Method (PDM) is the scheduling technique that identifies both successor and predecessor activities, assisting the project manager in sequencing project work. PDM represents activities as nodes and connects them with arrows to show the dependencies. It is the most common approach used in project management for constructing project schedules.
A is right answer.