Exam PMP All QuestionsBrowse all questions from this exam
Question 1

A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take a leave.

What should the project manager do next?

    Correct Answer: A

    When a risk that was previously identified during project planning materializes, it is crucial to consult the risk register for the planned risk response. The risk register typically includes pre-defined actions and steps to address such identified risks, enabling the project manager to implement a well-thought-out response swiftly. This ensures the project remains on track with minimal disruptions. Therefore, the project manager should consult the risk register for an appropriate planned risk response and implement it.

Discussion
Hao2Option: A

Hint is PM already identified this risk during Project Planning. Output of Identify Risk process is Risk register. Basically, a good PM w/ 4 values & 12 principles under PMI languages need to do this task with due diligent thus Risk register can be used later as sufficient reference regarding risk response plan when relevant risk happen. A is still the correct answer.

Acumen88

Considering that the risk has been identified during project planning, the PM needs to consult the risk register to ascertain if there is a response to this risk. The answer is A.

hatanaokiOption: A

A is correct. From Takedajuku perspective, if you study for 4 days and spend 2 days reviewing, you will have a better chance of passing the exam.

AditechOption: A

A. The project manager should immediately activate the contingency plan they developed during project planning to address this specific risk. This may involve reallocating resources, outsourcing the task, or adjusting the project schedule to accommodate the absence. Communication with stakeholders about the situation and the proposed solution is also crucial to manage expectations and minimize disruptions.

Anh_123Option: A

Choose A

AlonsochavesOption: A

If the PM identified the risk in case the resources is not available, the proper solution would be to review the risk log and find steps as recorded.

DMHROption: A

ANSWER - A

BuviDOption: A

A. Consult the risk register for an appropriate planned risk response and implement.

vshreevj13Option: A

A. Consult the risk register for an appropriate planned risk response and implement.

Ravi4frenchOption: A

stake holders should be informed with updates

Raymond1105Option: A

B,C,D do not make sense, filtered A

kakahoanghuyOption: A

Answer is A

nemm235Option: A

Q1 - A

lan_thinkOption: A

answer A

Alphy07Option: A

The answer is A

rockyleeOption: A

The answer is A

itvanthong87Option: A

Risk response

Mahi_02021988Option: A

Answer is A